2013 |
Date |
Lead |
PROJECT |
Instrument |
Plan/Note |
Status |
Runtime Report |
Sep 18 | Neyman | E345N2L: Keck Foundation/UCLA PSF-R (5 hours) | NIRC2-L | ||||
Ragland | E331N2L: NSF PSF-R (5 hours) | ||||||
Sep 13 | Doppmann | E326NS: NIRSPEC return to sky and non-sideral guiding (6 hr) | NIRSPEC | ||||
Ragland | E331N2: NSF PSF-R (4 hours) | NIRC2-N | |||||
Chock | E332N2: OBS 8-0-0 Release (1 hr piggyback) | ||||||
Chock | E334N2: NGWFC 7-1-1 Release (2 hr piggyback) | ||||||
Sep 12 | Panteleev | E321P: Phasing (1.5 hr) | PCS | ||||
Panteleev | E330P: Seg 22 Measurement (1 hr) | ||||||
Goodrich | E329S: TCSU Elevation Probe (5.5hr) | SSC | |||||
July 31b | Ragland | E347N2L: On-axis Point Spread Function Determination | NIRC2-L | ||||
July 24b | Ragland | E348N2: Improved LBWFS: low order aberations | NIRC2-N | ||||
June 25b | Ragland | E347N2L: On-axis Point Spread Function Determination | NIRC2-N | ||||
June 22b | TBD | Give-Back Science | TBD | ||||
June 17b | Doppmann | E341NS: NIRSPEC Sensitivity and Throughput (3hr) | NIRSPEC | ||||
Panteleev | E340NS: IQM Guider Focus Uniformity (0.5hr) | ||||||
Panteleev | E321P: Phasing (1.5hr) | PCS | |||||
June 14b | TBD | Give-Back Science | TBD | ||||
May 27a | L. Chock | E343NL: Release new epcom & /kroot (3hr) | NIRC2-L | ||||
Neyman | E345NL: AO Optimization (2hr) | ||||||
May 24 | Panteleev | E321P: Phasing (1.5hr) | PCS | ||||
Chin | E344P: f/15 Checkout (0.5hr) | ||||||
Neyman | E345NL: AO Optimization (2hr) | NIRC2-L | E343NL piggyback, but will not revert during 1st 2hr block | ||||
L. Chock | E343NL: Release new epcom & /kroot (4hr) | New s/w for at least 1st 6hr of NIRC2 time | |||||
Neyman | E345NL: AO Optimization (2hr) | ||||||
Apr 22a | Panteleev | Phasing (1.5hr) | PCS | ||||
Ragland/Neyman | On-axis PSF determination (3.5hr) | NIRC2-N | |||||
L. Chock | Release new epcom & /kroot | ||||||
Mar 31b | Panteleev | Phasing (1.5hr) | PCS | ||||
Wirth | DEIMOS engineering | DEIMOS | |||||
Mar 26 | TBD | Give-Back Science | TBD | ||||
Mar 25 | TBD | Give-Back Science | TBD | ||||
Mar 24 | TBD | Give-Back Science | TBD | ||||
Mar 07a | TBD | Give-Back Science | ESI | ||||
Feb 24b | Ragland/Neyman | On-axis PSF determination (4.5hr) | NIRC2-L | ||||
L. Chock | Release new epcom & /kroot | ||||||
Panteleev | PMFM with temperature (1hr) | PCS | |||||
Feb 02b | Ragland/Neyman | Low-order aberration (5.5hr) | NIRC2-N | ||||
L. Chock | Release new epcom & /kroot | ||||||
Feb 01b | Panteleev | Phasing (1.5hr) | PCS | ||||
Panteleev | PMFM with temperature (1hr) | ||||||
Doppmann | NIRSPEC sensitivity & throughput (3hr) | NIRSPEC | |||||
Jan 25b | Krasuski | TCSU engineering | SSC | ||||
2012 |
Date |
Lead |
PROJECT |
Instrument |
Plan/Note |
Status |
Runtime Report |
Dec 29 | TBD | Give-Back Science | TBD | ||||
Dec 28a | Neyman | AO Optimization (3hr) | NIRC2-L | ||||
Ragland/Neyman | On-axis PSF determination (2.5hr) | NIRC2-N | |||||
Dec 19 | Panteleev | Phasing (1.5hr) | PCS | ||||
Ragland/Neyman | On-axis PSF determination | NIRC2-N | |||||
Ragland/Neyman | LBWFS low order aberration | ||||||
Nov 27a | P. Tucker | Adjustment of K2 laser focus (2hr) | NIRC2-L | ||||
Ragland/Neyman | On-axis PSF determination (3.5hr) | NIRC2-N | |||||
Nov 27b | Burgasser | Give-Back Science | NIRSPEC | ||||
Nov 26 | McLean/Burgasser | Give-Back Science | NIRSPEC | ||||
Nov 01a | Engineering | SegEx | PCS+SSC | ||||
Nov 01b | Panteleev | Segment aberration with elevation | |||||
Krasuski | Pointing tests | ||||||
Oct 31 | Engineering | SegEx | PCS+SSC | ||||
Oct 30 | Engineering | SegEx | PCS+SSC | ||||
Oct 01 | Neyman/Campbell | NIRC2 checkout & PSF determination | NIRC2-N | ||||
Sep 27a | Engineering | SegEx | PCS+SSC | ||||
Sep 27b | S. Kwok | KCWI guiding tests | ACAM+SSC | ||||
Sep 26 | Engineering | SegEx | PCS+SSC | ||||
Sep 25 | Engineering | SegEx | PCS+SSC | ||||
Sep 01b | Neyman | AO Optimization | NIRC2-L | ||||
Aug 31a | Engineering | SegEx | PCS+SSC | ||||
Aug 31b | Armandroff | TK science | NIRSPEC | ||||
Aug 30 | Engineering | SegEx | PCS+SSC | ||||
Aug 29 | Engineering | SegEx | PCS+SSC | ||||
Aug 02 | Armandroff | TK science | NIRSPEC | ||||
Aug 01 | Panteleev | Shutdown recovery | PCS+SSC | ||||
Doppmann | NIRSPEC post-service checkout | NIRSPEC | |||||
Jul 31 | shutdown | ||||||
Jul 30 | shutdown | ||||||
Jul 27 | Panteleev | Phasing | PCS | ||||
Woillez, Ragland | ASTRA/V2 Engineering | ASTRA/V2 | |||||
Jun 29a | Engineering | SegEx | PCS | ||||
Jun 29b | Campbell | NIRSPAO & NIRC2 engineering | NIRSPAO/NIRC2-N | ||||
Jun 28 | Engineering | SegEx | PCS | ||||
Jun 27 | Engineering | SegEx | PCS | ||||
Jun 26 | Armandroff | Team Keck Science | NIRC2-L | ||||
Merline | Give-Back Science | ||||||
Jun 25a | New Horizon | Give-Back Science | NIRC2-N | ||||
Jun 25b | Campbell | AOAcq improvements/N2 spectroscopy | |||||
Jun 24 | New Horizon | Give-Back Science | NIRC2-N | ||||
Armandroff | Team Keck Science | ||||||
Jun 01a | Engineering | SegEx | PCS | ||||
Jun 01b | Kwok | MAGIQ maintenance & release (2hr) | NIRSPEC | ||||
Krasuski | Open loop tracking | SSC | |||||
May 31 | Engineering | SegEx | PCS | ||||
May 30 | Engineering | SegEx | PCS | ||||
May 29 | Woillez | Low order abberations in dual NGS (3hr) | NIRC2-N | ||||
Campbell | AOAcq improvements/N2 spectroscopy (2hr) | ||||||
Wirth | DEIMOS engineering (4hr) | DEIMOS | |||||
May 10a | Engineering | SegEx | PCS | ||||
May 10b | Krasuski | Open loop tracking | SSC | ||||
May 09 | Engineering | SegEx | PCS | ||||
May 08 | Engineering | SegEx | PCS | ||||
Apr 29 | Panteleev | Phasing | PCS | ||||
Woillez, Ragland | ASTRA/V2 Engineering | ASTRA/V2 | |||||
Mar 07 | Panteleev | Phasing | PCS | ||||
Lyke | Post-service verification | NIRSPEC | |||||
Feb 09a | Neyman | PSF recovery | NIRC2-N | ||||
Feb 08a | Panteleev | Phasing | PCS | ||||
Panteleev | Phase-stacking crosstalk (1.25hr) | PCS | |||||
Woillez | ASTRA/V2 Engineering | ASTRA/V2 | |||||
Feb 07 | Lyke | LBWFS 20x20 vs 5x5 | NIRC2-L | ||||
Lyke | AOAcq improvements | ||||||
Lyke | Optimize LBWFS 5x5 performance | ||||||
Ragland | IF observations in LGS mode (3hr) | IF-L | |||||
Woillez | ASTRA: dual field acquisition (3hr) | IF-V2 DFPR | |||||
Feb 06 | Lyke | LBWFS 20x20 vs 5x5 | NIRC2-L | ||||
Lyke | AOAcq improvements | ||||||
Lyke | Optimize LBWFS 5x5 performance | ||||||
Woillez | Low order abberations in dual NGS (2hr) | NIRC2-N | |||||
2011 |
Date |
Lead |
PROJECT |
Instrument |
Plan/Note |
Status |
Runtime Report |
Proposals for 2011B Q2 | |||||||
Jan 07a | Panteleev | Phasing (1.5hr) | PCS | ||||
Panteleev | MAGIQ IQM (0.75hr) | NIRSPEC | |||||
Krasuski | Open loop tracking (3.25hr) | SSC | |||||
Nov 05a | Ragland | V2 SPR Engineering | V2 SPR | ||||
Nov 04a | Panteleev | Phasing | PCS | ||||
Ragland | ASTRA/V2 Engineering | ASTRA/V2 | |||||
Proposals for 2011B Q1 | |||||||
Oct 12 | Neyman | AO PSF Recovery (4 hrs) | NIRC2 - NGS | contingent on successful post-sm engineering for NIRC2 | |||
Engineering | TBD | ||||||
Oct 09 | Panteleev | Phasing (1.5hr) | PCS | ||||
Ragland | IF engineering | ASTRA/V2 | |||||
Oct 06 | TBD | Give-Back Science | NIRSPEC | ||||
Oct 05 | Tran | Post-service mission engineering | NIRC2 - NGS | ||||
Oct 04 | TBD | Give-Back Science | TBD | ||||
Oct 03 | TBD | Give-Back Science | TBD | ||||
Sep 21a | Campbell | LGS-AO engineering | OS/N2-L | ||||
Sep 15 | TBD | Give-Back Science | TBD | ||||
Sep 14 | TBD | Give-Back Science | TBD | ||||
Sep 10 | Ragland | IF engineering | ASTRA/V2 | ||||
Sep 07a | Panteleev | Phasing (1.5hr) | PCS | ||||
Panteleev | MAGIQ IQM for nirspec | NIRSPEC | |||||
Sep 07b | TBD | Give-Back Science | TBD | ||||
Sep 06 | TBD | Give-Back Science | TBD | ||||
Sep 05 | TBD | Give-Back Science | TBD | ||||
Sep 04 | TBD | Give-Back Science | TBD | ||||
Aug 30a | Wirth | ESI engineering | ESI | ||||
Proposals for 2011A Q2 | |||||||
Jul 14b | Tran | Pre-service mission engineering | NIRC2 - NGS | ||||
Jun 23a | IF Engineering | IF - Nuller | |||||
Jun 23b | TBD | Give-Back Science | TBD | ||||
Jun 22b | Neyman | PSF Recovery | NIRC2 - NGS | ||||
Jun 21b | Neyman | PSF recovery | NIRC2 - NGS | ||||
Jun 14 | Lyke | NIRSPAO engineering | NIRSPAO - L | ||||
Krasuski | Pointing test | SSC | |||||
Panteleev | Telescope throughput | ||||||
Jun 13b | TBD | Give-Back Science | TBD | ||||
Jun 12b | TBD | Give-Back Science | TBD | ||||
Jun 11 | Panteleev | Phasing (1.5hr) | PCS | ||||
Ragland | ASTRA engineering | IF | |||||
IF Engineering | IF - V2 | ||||||
May 19 | Panteleev | Phasing (1.5hr) | PCS | ||||
Woillez | ASTRA engineering | IF | |||||
May 11 | Lyke | Nirspec engineering | NIRSPEC | Guiding drift engineering has priority on all other tests. JL to talk with SP about Magiq IQM. | |||
Panteleev | MAGIQ IQM for nirspec | ||||||
Kwok | MAGIQ maintenance release | ||||||
Proposals for 2011A Q1 | |||||||
Mar 19 | Panteleev | Phasing (1.5hr) | PCS | ||||
Woillez | ASTRA engineering | IF | |||||
Feb 12a | Panteleev | Phasing (1.5hr) | PCS | ||||
IF | IF engineering | Nuller | |||||
Proposals for 2010B Q2 | |||||||
Jan 21a | Woillez | ASTRA DFPR | IF | ||||
Panteleev | Phasing (1.5hr) | PCS | |||||
2010 |
Date |
Lead |
PROJECT |
Instrument |
Plan/Note |
Status |
Runtime Report |
Dec 22a | Panteleev | Phasing (1.5hr) | PCS | ||||
Woillez | ASTRA DFPR | IF | |||||
Dec 07 | Lyke | NIRSPAO engineering | NIRSPAO | ||||
Krasuski | TCSU Azimuth Control Loop (3hr) | ||||||
Panteleev | K2 UFS test (1.5hr) | PCS | |||||
Nov 23a | Ragland | V2-SPR | IF | ||||
Nov 22 | Panteleev | Phasing (1.5hr) | PCS | ||||
Woillez | ASTRA DFPR | IF | |||||
Chock | WYKO PC software release | piggyback | SW release, no sky time | ||||
Ulander | K2 local control ethernet addition | daytime only | no sky time needed | ||||
Proposals for 2010B Q1 | |||||||
Oct 24a | E. Wright | Give-Back Science | NIRSPEC | ||||
Oct 18a | Woillez | ASTRA DFPR | IF | ||||
Oct 05a | Wirth | DEIMOS Performance Monitoring | DEIMOS | ||||
Sep 24a | Panteleev | Phasing (1.5hr) | PCS | ||||
Engineering | SegEx | PCS | |||||
Sep 24b | Carpenter | Give-Back Science | NIRC2-NGS | ||||
Sep 23 | Engineering | SegEx | PCS | ||||
Sep 22 | Engineering | SegEx | PCS | ||||
Aug 26 | Campbell | K2 LGS | OS/N2 - LGS | ||||
Neyman | AO PSF Reconstruction | N2 - NGS | |||||
Aug 25a | Panteleev | Phasing (1.5hr) | PCS | ||||
Engineering | SegEx | PCS | |||||
Aug 24 | Engineering | SegEx | PCS | ||||
Proposals for 2010A Q2 | |||||||
Jul 25a | Lyke | OSIRIS Throughput | OSIRIS-NGS | ||||
E. Chock | AO or DCS SW release | SW release, no sky time | |||||
Jul 24a | TBD | Give-Back Science | NIRSPEC | ||||
Jul 23a | Panteleev | Phasing (1.5hr) | PCS | ||||
Engineering | SegEx | PCS | |||||
Jul 22 | Engineering | SegEx | PCS | ||||
Jul 21 | Engineering | SegEx | PCS | ||||
Jul 20b | Woillez | V2 | V2 | ||||
Jul 19 | Woillez | ASTRA | ASTRA | ||||
Ulander | MOSFIRE local controls Modifications | K1 | Daytime test only, no skytime | ||||
Jul 16 | Woillez | ASTRA K2 only (2-3hr) | IF-K2 | need OSIRIS ->DSM 7/14 | |||
TBD | Give-Back Science | TBD | |||||
Jun 27 | TBD | Give-Back Science | TBD | ||||
Jun 25a | Panteleev | Phasing (1.5hr) | PCS | NIRSPEC in beam | |||
Engineering | SegEx | PCS | |||||
Jun 24 | Engineering | SegEx | PCS | ||||
Panteleev | Focus vs Elevation (2hr) | DEIMOS | |||||
Jun 23 | Engineering | SegEx | PCS | ||||
Wirth | DEIMOS Performance Monitoring (2hr) | DEIMOS | |||||
Jun 22 | Campbell | K2 LGS | OS/N2 - LGS | DEIMOS in beam | |||
E. Chock | AO or DCS SW release | SW release, no sky time | |||||
May 29b | Ragland | L-band science mode characterization | Nuller | ||||
May 28 | TBD | Give-Back Science | NIRSPEC | some contingency time for ACS upgrade | |||
May 27 | Cohen | CPH-30 with ACS upgrade (4hr) | PCS, SSC | ||||
Panteleev | PCS UFS (1hr) | PCS | |||||
Hill | IPM task #24: check rotator (4hr) | NIRSPEC | |||||
E. Chock | AO or DCS SW release | SW release, no sky time | |||||
Proposals for 2010A Q1 | |||||||
Apr 23a | Panteleev | Phasing (1.5hr) | PCS | ||||
Wolliez | ASTRA DFPR (4hr) | IF | |||||
Apr 02a | Panteleev | Phasing (1.5hr) | PCS | ||||
Engineering | SegEx | PCS | |||||
Apr 01 | Cohen | K2 ACS upgrade (5hr) | PCS | ||||
Engineering | SegEx | ||||||
Mar 31 | Cohen | K2 ACS upgrade (5hr) | PCS | ||||
Engineering | SegEx | ||||||
Mar 30 | Wolliez | ASTRA DFPR | IF | ||||
Ragland | ASTRA sequencer test | NIRC2 | |||||
Mar 29b | Campbell | K2 LGS steering and SW release (4hr) | NIRC2-LGS | ||||
Ragland | ASTRA sequencer test (1hr) | NIRC2 | |||||
Feb 24a | Panteleev | Phasing (1.5hr) | PCS | ||||
Goodrich | Scintillometer impact on guider | NIRSPEC | T1042 | ||||
Ragland | V2 engineering | IF | |||||
Proposals for 2009B Q2 | |||||||
Jan 22 | S. Panteleev | Focus vs. Elevation (2hr) | ESI | ||||
G. Wirth | IFU commissioning + MAGIQ SW | ||||||
2009 |
Date |
Lead |
PROJECT |
Instrument |
Plan |
Status |
Runtime Report |
Dec 29 | S. Panteleev | Phasing (1.5hr) | PCS | ||||
J. Woillez | ASTRA DFPR | IF | |||||
Dec 04a | Engineering | SegEx | PCS | ||||
Dec 03 | Engineering | SegEx | PCS | ||||
Dec 02 | Engineering | SegEx | PCS | ||||
Nov 07a | TBD | Give-Back Science | NIRSPEC | ||||
Proposals for 2009B Q1 | |||||||
Oct 30a | Engineering | SegEx | PCS | ||||
Oct 29 | Engineering | SegEx | PCS | ||||
R. Cohen | ACS upgrade | ||||||
Oct 28 | Engineering | SegEx | PCS | ||||
R. Cohen | ACS upgrade | ||||||
A. Conrad | Mars tracking test | NIRC2 | done | nightlog | |||
Moon test | |||||||
NIRC2 exposure time | |||||||
Oct 26b | CIT | Give-Back Science | NIRSPEC | ||||
Oct 24a | IF Engineering | IF Engineering | Nuller | ||||
Oct 09 | Larkin | Give-Back Science | OSIRIS-N | ||||
Oct 01 | S. Panteleev | SegEx, phasing,PCS vs El, SUFS? | PCS | done | nightlog | ||
S. Kwok | Pointing test (2hr) | ||||||
S. Kwok | MAGIQ software update (3.5hr) | NIRSPEC | |||||
Sep 30 | Engineering | SegEx | PCS | ||||
Sep 29 | Engineering | SegEx | PCS | ||||
Sep 03a | R. Campbell | OSIRIS post-service checkout | OSIRIS-L | done | nightlog | ||
E. Chock | SW release | ||||||
Sep 02a | S. Panteleev | SegEx, phasing, PCS vs El, SUFS? | PCS | ||||
Sep 02b | Macintosh | Give-Back Science | OSIRIS-N | ||||
Sep 01 | Engineering | SegEx | PCS | ||||
Aug 31 | Engineering | SegEx | PCS | ||||
Aug 30 | Macintosh | Give-Back Science | NIRC2 | ||||
Aug 28a | J. Woillez | ASTRA DFPR | IF | lost to weather | nightlog | ||
Aug 28b | UH | Give-Back Science | NIRSPEC | ||||
Aug 27a | S. Panteleev | PCS UFS (2hr) | PCS | done | nightlog | ||
J. Woillez | ASTRA DFPR (2.5hr) | IF | |||||
Aug 27b | A. Conrad | Mars tracking test | NIRC2-N /NIRSPEC | ||||
E. Chock | SW release | ||||||
Aug 26a | Campbell | IR dichroic characterization | NIRC2-N | ||||
A. Conrad | Moon test | not done due to technical problems | nightlog | ||||
Aug 26b | UH | Give-Back Science | DEIMOS | ||||
Sat | Mar 07a | S. Panteleev | Phasing (1.5hr) | PCS | night lost to weather | ||
R. Cohen | ACS Upgrade (4hr) | PCS | |||||
Sat | Feb 07 | S. Panteleev | Phasing (1.5hr) | PCS | entire night lost to weather
|
||
R. Cohen | ACS Upgrade (4hr) | PCS | |||||
T. Krasuski | Pointing tests (2hr) | PCS | |||||
S. Panteleev | Magiq guider focus map (2hr) | NIRSPEC | |||||
J. Lyke | MAGIQ PO | NIRSPEC | |||||
L. Chock | New DCS release (no sky time) | ||||||
Sun | Feb 01a | R. Campbell | LGS AO Engineering | NIRC2/OSIRIS | done | ||
Tue | Jan 27a | R. Cohen | PCS | postponed | |||
G. Wirth | MAGIQ flexure compensation (5hr) | DEIMOS | done | nightlog | |||
2008 |
Date |
Lead |
PROJECT |
Instrument |
Plan |
Status |
Runtime Report |
Wed | Dec 10b | S. Panteleev | Phasing (1.5hr) | PCS | night lost to weather | ||
J. Lyke | MAGIQ PO (3hr) | NIRSPEC | |||||
T. Krasuski | Encoder & analog board tests (1hr) | postponed | |||||
Sun | Nov 09b | S. Panteleev | Phasing (1.5hr) | PCS | done | nightlog | |
J. Lyke | MAGIQ Guiding (2hr) | NIRSPEC | |||||
A. Conrad | Differential TSS Tracking (2hr) | NIRC2 | |||||
Sat | Oct 11b | S. Panteleev | Phasing | PCS | |||
J. Lyke | MAGIQ Image Quality (4hr) | NIRSPEC | |||||
Tue | Sep 16 | S. Panteleev | IQ and Throughput (0.25hr) | SSC | T1030 | ||
Le Mignant | PSF reconstruction (4hr) | NIRC2-L | |||||
Van Dam | 5x5, 20x20 Lensets Verification (5hr) | NIRC2-L | |||||
E. Johansson | NGWFC 4.2 | AO | SW test - no sky time | ||||
E. Chock | New AO SC, OBS | AO | SW test - no sky time | ||||
Fri | Sep 12 | Post-shutdown checkout | |||||
MAGIQ? | NIRSPEC | ||||||
Thu | Aug. 21 | TBD | Give-Back Science | TBD | |||
Tue | Aug 19 | TBD | Give-Back Science | TBD | |||
Thu | Aug 14b | S. Panteleev | Phasing | PCS | |||
S. Ragland | L-band Science Verification | IF | |||||
Wed | Aug 13 | TBD | Give-Back Science | NIRSPEC | |||
Tue | Aug 12 | TBD | Give-Back Science | NIRSPEC | |||
Mon | Aug 11 | S. Panteleev | IQ and Throughput (0.25hr) | SSC | T1030 | ||
G. Wirth | MAGIQ (3hr) | DEIMOS | |||||
Le Mignant | PSF reconstruction (3hr) | NIRC2-N | |||||
A. Conrad | L-band Spectroscopy (2hr) | NIRC2-N | |||||
A. Conrad | VA Differential Tracking (1hr) | NIRC2-N | |||||
E. Chock | New AO SC, OBS | AO | SW test - no sky time | ||||
Sun | Jul 20 | J. Woillez | ASTRA SPR | IF | |||
Sat | Jul 19 | Muno | Give-Back Science | NIRSPEC | |||
Fri | Jul 18 | S. Panteleev | Throughput (0.5hr) | SSC | T1030 | ||
J. Lyke | MAGIQ | NIRSPEC | |||||
Thu | Jul 17 | Le Mignant | PSF reconstruction (3hr) | NIRC2 | |||
J. Lyke | MAGIQ (6hr) | NIRSPEC | |||||
Sat | Jul 12b | S. Panteleev | Phasing | PCS | Phasing to be done during configuration change | ||
J. Woillez | ASTRA SAT (2hr) | IF | |||||
J. Woillez | ASTRA SPR (2.5hr) | ||||||
Thu | Jul 10 | Macintosh | Give-Back Science | NIRC2-NGS | |||
Sun | Jul 06 | S. Panteleev | Inst. Guider Calibration (1hr) | DEIMOS | |||
S. Kwok | MAGIQ (3.5hr) | ||||||
G. Wirth | Performance Monitoring (4.5hr) | ||||||
Tue | Jun 24 | Madau | Give-Back Science | NIRSPEC | |||
Thu | Jun 5 | Le Mignant | PSF reconstruction (2.5hr) | NIRC2 | |||
A. Conrad | L-band Spectroscopy (2hr) | NIRC2 | |||||
A. Conrad | VA Differential Tracking (1hr) | NIRC2 | |||||
J. Lyke | 100mas Background (3.5hr) | OSIRIS | |||||
Fri | May 23b | S. Panteleev | Phasing (1.5hr) | PCS | |||
J. Woillez | ASTRA SPR (3hr) | IF | |||||
Sat | May 17 | J. Lyke | MAGIQ | NIRSPEC | |||
Tue | Apr 22b | S. Ragland | Validation of L-band mode (1hr) | IF | |||
Le Mignant | AO PSF reconstruction (4hr) | NIRC2 | |||||
Sat | Apr 12b | S. Panteleev | Phasing (1.5hr) | PCS | T962a | ||
Pott | ASTRA angle tracking (1hr) | IF | |||||
J. Woillez | ASTRA (2.5hr) | IF | |||||
Fri | Mar 14b | S. Panteleev | Phasing (1.5hr) | PCS | T962a | ||
J. Lyke | MAGIQ (4hr) | NIRSPEC | |||||
Thu | Mar 13 | J. Lyke | MAGIQ commissiong (11hr) | NIRSPEC | |||
Mon | Feb 18b | Pott | ASTRA angle tracking (1hr) | IF | done | report | |
J. Woillez | ASTRA (4.5hr) | IF | done | ||||
Thu | Feb 14b | S. Panteleev |
Phasing and Super UFS (3hr) | PCS | T962a | done | |
R. Campbell | Differential tracking (2.5hr) | NIRC2 | done | nightlog | |||
Sat | Jan 26 | S. Panteleev | Phasing (1.5hr) | PCS | |||
Djorgovski | Give-Back Science | NIRSPEC | |||||
Mon | Jan 21 | S. Kwok | MAGIQ | NIRSPEC | |||
Sun | Jan 20 | S. Ragland | AO Chopping Validation (1hr) | AO | done | nightlog | |
TK science & other AO Engineering | NIRSPEC | ||||||
Sat | Jan 19 | S. Kwok | MAGIQ commissioning (11hr) | NIRSPEC | |||
Fri | Jan 18 | S. Kwok | MAGIQ | ||||
Thu | Jan 17 | S. Kwok | MAGIQ commissioning (11hr) | NIRSPEC | |||
Wed | Jan 16b | D. Le Mignant | NGS-AO engineering (5.5hr) | NIRC2/OSIRIS | done | nightlog | |
2007 |
Date |
Lead |
PROJECT |
Instrument |
Plan |
Status |
Runtime Report |
Fri | Dec 28 | S. Kwok | MAGIQ | NIRSPEC | |||
Thu | Dec 20 | S. Panteleev | Phasing (1.5hr) + whatever needs to be checked out after K2 shutdown | PCS | |||
S. Kwok | MAGIQ | NIRSPEC | |||||
Thu | Nov 29 | J. Lyke | NIRSPAO engineering + AO (5hr) | NIRSPAO | done | ||
S. Kwok | MAGIQ (6hr) | some done; closed for 3 hrs due to weather | |||||
Mon | Nov 26b | S. Kwok | MAGIQ (4.25hr) | NIRSPEC | entire night lost to weather | ||
J. Woillez | ASTRA (1.25hr) | IF | |||||
Sat | Nov 24 | S. Panteleev | Phasing (1.5hr) | PCS | done | nightlog | |
S. Panteleev | Super UFS (4hr) | PCS | |||||
S. Kwok | MAGIQ (5.5hr) | NIRSPEC |
Old Schedules