Keck Engineering Observing Time Policy
and
The Engineering Time Allocation Committee, E-TAC
Hilton Lewis and Bob Goodrich
1 May 2003
Mission
To provide structure and accountability to the Keck engineering programs and
results.
To more quickly identify unneeded engineering nights so that they may be given
back to science.
Charge
The engineering time allocation committee (E-TAC) will:
- Review total engineering requests for the upcoming semester, and
propose a total package to the Observatory Director and Deputy Directors.
- Review individual engineering requests during the semester, on a quarterly
basis. Schedule, prioritize, and request clarification when necessary.
- Follow up on results from scheduled engineering tests.
- Provide feedback
on engineering results and usage for the SSC and/or CARA Board.
- Identify
science give-back nights in a timely manner, to allow institutions to solicit
programs for their use.
The E-TAC process
In the era of increased competition for Observing resources, it is vital that
we use engineering observing time effectively. We propose to modify our current
approach to make it easier to communicate engineering results and to better
focus our efforts to use engineering time as efficiently as possible
Current process
The allocation of engineering time is based on known needs (e.g. segment exchanges),
upcoming projects (e.g. instrument commissioning) and experience (e.g. minor
upgrades, testing of fixes). Typically the Observing Support Coordinator (currently
Barbara Schaefer) conducts a survey to ascertain engineering needs for the
upcoming semester, and then allocates nights based on the feedback received,
after discussion with the Observatory Director, Deputy Directors, and other
principals.
Planning for the actual engineering nights is left up to the groups interested
in having the tests performed. There is little feedback to the wider Observatory
on what the goals of the tests are, or what was accomplished.
Proposed new process
We propose that in future we adhere to the following process:
- The Observing Support Coordinator will solicit written requests for
engineering time in January and July of each year, for use in preparation
of the next semester’s
schedule.
- The Keck Engineering TAC will allocate
engineering time to proposals, based
on these written requests. The requests should include: purpose of the test(s),
time required, telescope and instrumentation configuration and preferred
date/time. The successful requests will are posted in the engieering schedules
for Keck I and Keck
II.
- As soon as
possible, but no later than two weeks prior to the engineering run, the
PIs for the engineering to be conducted will submit a detailed test
plan, describing the tests to be performed, their durations and detailing
all logistical needs (e.g. staff requirements, transportation, lodging, support).
It is the responsibility of the PI to make all logistical arrangements. The
plans will be reviewed by the Engineering TAC for completeness and will then
be posted on the web, linked to the original requests.
- One week prior to the
engineering run, the E-TAC Czar (currently Randy Campbell) will distribute
a detailed time breakdown of the upcoming run, along
with the test plan, to CARA staff and the PIs.
- There will be quarterly reviews
of all engineering tests conducted over the previous quarter. These reviews
may occupy one of the Support Astronomer meetings or a special Engineering
Meeting may be called. PIs are expected to present any results
(interim or final) at these
reviews. These results and reports will be posted on the web, linked to the
original proposals.
The ability of PIs to utilize previously allocated time in an efficient manner
and to analyze and present existing data in a timely fashion will be a factor
in considering the allocation of future engineering time.
Special cases:
- Routine engineering tests—segment exchanges, phasing, stacking and pointing
tests—will be scheduled by the Observing Support Coordinator.
- Engineering projects related to interferometry must be coordinated through
the interferometry group. The E-TAC does not handle interferometry engineering.
- Commissioning plans for new facility instruments should be coordinated
through the Support Astronomer in charge, for the case of new instruments.
Details
of commissioning tasks and results are expected, however they may be organized
differently than other engineering requests. For example, the commissioning
punch list and results may be hosted on the instrument’s Web page rather
than the E-TAC’s Web page.