Echellette Spectrograph and Imager
Tasks, Tests and Results
Weekly schedule of who has control of
the instrument (Assembly, testing, alignment, ...)
Tasks To Do
- DONE...Align collimator to bearing.
- DONE...Focus collimator.
- Measure location of slit mask.
- Align collimator actuators to optical axis. (Requires darkness)
- Align grating.
- Align prisms.
- Align camera.(Requires darkness)
- Translation of axis with laser.
- Tilt with spectra.
- Align imaging mirror.
Test Requested
- List of "ESI Precommisioning
Tasks" requested by Keck (Bob Goodrich)
- Optical
- Perform interferrometric analysis of the two mirror stages, and
the prism stage, to determine deflections of fully loaded stages at
various spacial orientation.
- Measure actual field location of the optical center of the
filter wheel.
- Measure collimator actuator alignment to telescope axis.
- Check focus of collimator
- Measure instrument flexure over full range of travel.
(Requires darkness)
- Mechanical
- Determine positioning repeatability of post dispersion prism.
(Requires darkness)
- Determine positioning repeatability of imaging mirror.
(Requires darkness)
- Remove and re-install grating to determine positioning
repeatability. (Requires darkness)
- Electrical
- Software
- Other
Submit a request
Results
- Optical
- Mechanical
- Ran slit mask wheel under servo control. Rotation target of 2
RPM achieved. Steel belt tracked well with slight vertical displacement
upon direction reversal. All three (slit mask, filter, aperture) wheels
were operated under servo control at 0 degrees C. Sample torques at this
temperature were; .15-.68, .21-.72, .09-.69 Amps. Warm torques of; .11-.60,
.12-.69, .24-.52 Amps show that no unexpected binding occured while
operating a near zero temps.
- Width of Renishaw magnetic fiducial found to be ~76 microns
using the slit mask wheel to measure it. Backlash (including windup) of the wheel was measured to be about 15 microns in it's current configuration.
- Electrical
- Software
- Collimator actuators ran from limit to limit while supporting a
simulated collimator. Ganged motion of all three actuators operating
under dual-loop mode performed well.
- GUI and control software operational and controlling 10 of 12
stages. CCD exposures now under GUI control.
- Other
- Temperature sensors