NIRSPEC Reliability Improvement 
Progress report:  6  May  2004

Overview:

With the impending release of new server codes that (it is hoped) will greatly reduce server crashes the project finds itself at a crossroads.     Several options exist and this report attempts to examine some of them in the context of the project's history,  goals, budget and schedule.

Project History and Plan:

By mid-summer of 2003 it was clear that the rate of server crashes had risen considerably and significant time was being lost on sky.    What would become the first phase of the NIRSPEC reliability improvement project began around this time.     Most of the current team members were involved from this early point.

With the increased resources that resulted from formal project status in October 2003,   work on phase I was able to accelerate, while phase II was planned and proceeded in parallel.     A third phase was envisioned at this point but detailed planning would require the results of phase II.

Overall goals would be achieved via phase III and are described below.     At the outset, due to the nature of the project, the budget and schedule were educated guesses.      To date,  we have overspent the original manpower estimate of 0.79 FTE by about 25 percent.     None of the $10K set aside for procurement has been spent.     We are currently one month behind the originally envisioned schedule.

Phase I:   Speed recovery from server crashes.

Phase II:   Determine cause(s)  of server crashes.

Phase III:   Prevent server crashes.

Proceeding From Here:

As mentioned above, there is some question how we proceed from here.   A number of project tasks remain to be completed: There exist ways to improve the reliability of NIRSPEC which are currently not within the purview of this project: Finally, note that via this project we have used (so far) roughly 1.0 FTE to gain about 5 percent of time on sky.    A NIRSPEC efficiency improvement project would gain more time on sky with similar or less effort.     Currently, 20 to 25 percent of time on sky is claimed lost due to instrument inefficiency.     For example: We are faced with the question of how and when to ramp down this project.    Three options are suggested:

1.    End the project now.

2.    Maintain the project to the end of semester 2004A.

3.    Continue through FY04.