K2 LGS AO test plan, Sept 17, 18, 19 HST
(including imaging LGS from K1)
Test Duration (hr)
9/17
- NGS setup, calibr for LGS 0.5
- STRAP parameters testing 2
- LBWFS testing 1
- TSS testing 0.5
- NGS/STRAP setup
- calibr for LGS 1
- Alignment 2
- WFS diag of LGS 0.5
- pointing / centering / LSGOMI 2
- LGS on LBWFS and ACAM 1
- Image LGS w/ K1 2
9/18
- NGS setup, calibr for LGS 0.5
- STRAP parameters testing
on dim stars 2
- LBWFS testing 1
Alignment 0.5
- 1st LGS image: bright star
on-axis 2
- 1st LGS image: dim star
on-axis 2
- 1st LGS image: bright t/t star
off-axis 1
Image LGS w/ K1 (contingency) 2
9/19
- NGS setup, calibr for LGS 0.5
- STRAP parameters testing on
dim stars 1
- LBWFS testing 0.5
Alignment 1
- 1st LGS image: bright t/t star
off-axis 2
- 1st LGS image: dim t/t star
off-axis 3
- LGS Stability 0.5
- Beam Quality by Elevation 2
- LGS Stability (if time permits) 0.5
- contingency
- STRAP + DM performance in
- NGS mode 3
- LBWFS plate scale 0.5
- tip/tilt error_10 testing 1