pointing test.

1. PI: Shui Kwok, OA to perform test.
2. Purpose: pointing test.
3. Engineering test: T20b (from remedy).
4. Duration: 3.5hrs.
5. Description: see T920.
6. Telescope: Keck 1, SSC.
7. Data reduction: manual with TPOINT.
8. Preferred date: January 2005.
9. On going monitoring of telescope pointing model.