K1AO engineering run

Final test plan

Sunday, July 6, 2003.

5:00:   AO system calibration (David)

6:00:   Verify new release of OBS with FCS and WPS tracking shaper fix. (Scott)

            Twilight test with some additional testing during Kelle’s tests below.

7:30:   Auto-acquisition tests (Kellee)

2 hours dedicated time plus additional tests in parallel with WFC tests below.

9:30    IDL procedure testing (David)

10:00  Verify newest release of K1 AO WFC (Erik, David)

1)     File I/O  (new SNL based File loads) (1/2 hour)

2)     Test Wavefront Sensor Focus Offloading work around (1 hour)

3)     Test new release of PRC with the following new features: (1/2 hour)

a.     Keyword interface between PRC and WFC

b.     Socket interface between PRC and WFC

4)     Test IDL reconstructor widget using socket interface (1/2 hour)

12:30            Characterize the severity of the WFC Telemetry stalls that are responsible for the focus offloading problem.  (Erik, David)

1:00    Look for tip/tilt offloading problems that could also be related to telemetry stalls. (Erik, David)

1:30            Performance tests (Erik, David)

Take open / closed loop diagnostics to support computing disturbance rejection curves. Perform tests on both bright and dim stars.

3:00            Pointing tests (Wayne)