Segment Exchange Plan For: 6/17/03 & 6/18/03
From: M. Dahler
Date: 6/10/03
A primary mirror segment exchange for Keck K1 is scheduled to take place on 6/17/03 and 6/18/03. The following is a schedule of the exchange and related activities (a detailed engineering observing schedule will be distributed separately).
![]()
EXCHANGE:
|
Day 1 |
Day 2 |
|||||
|
Segment Position: |
26 |
11 |
3 |
28 |
27 |
12 |
|
Remove Serial No.: |
27 |
17 |
55 |
89 |
76 |
74 |
|
Install Serial No.: |
69 |
11 |
57 |
40 |
37 |
18 |
![]()
SUPPORT ACTIVITIES:
Aluminization is complete: (Tim Saloga)
Sensor maintenance is completed: S. Doyle
Segment crane check-out, [ CARA Doc. 159] Completed: (A. Agliam)
CREW:
Team Leader:
N. Felton (Floor)
Mirror Technicians:
C. Hunt (Cell)
P. Crivello (Cell)
T. Arruda(Cell)
R. DeMotta (Cell)
T. Saloga (Floor)
M. Nakata (Floor)
Sensor Technicians:
D. Chan, J. Killian (Swing-out) Day1
D. Chan, G. Thorkildsen(Swing-out) Day2
S. Doyle, E. Appleby(Swing-in) Day1
S. Austria, D. Chan(Swing-in) Day2
S. Doyle (Appleby) (Warping) 6/18/03
G. Thorkildsen (Austria) (Warping) 6/19/03
Crane Operator:
A. Agliam, D. Scofield (Day 1)
A. Agliam, M. Devenot (Day 2)
![]()
Early Starts and Late Finishes:
Mirror, Crane and Sensor Swing-out crew start 2 hours EARLY.
Sensor technicians may stay LATE for sensor swing in.
![]()
Distribution:
D. Chan
R. Cohen
A. Contos
K. Kinoshita
H. Lewis
R. Matsuda
D. McBride
B. Moskitis
T. Nordin
B. Schaefer
J. Vause
P. Wizinowich
Crew:
A. Agliam
C. Hunt
D. Chan
D. Scofield
E. Appleby
G. Thorkildsen
J. Killian
M. Devenot
M. Nakata
N. Felton
P. Crivello
R. DeMotta
S. Austria
S. Doyle
T. Arruda
T. Saloga
ACTIVITY SCHEDULE FOR exchange dates: 6/17/03 and.6/18/03
MIRROR SEGMENT EXCHANGE
Day 1 6/17/03
Lead person
check that dome AC's are OFF
Lead person
check that JLG is stowed for segment exchange
SCHEDULE:
A.M. Remove SP. 26, 11, 3 Cell crew lunch break, Install 3.
P.M. Floor crew lunch break, Install SP 11, 26.
Warping : S. Doyle (Appleby) will warp segments on 6/18/03.
|
Remove |
|||||
|
SP |
SN |
telescope face |
(tel az / floor az) |
data sheet |
Removed |
|
26 |
27 |
-X+Y |
37.5 / --- |
12 |
|
|
11 |
17 |
-X+Y |
37.5 / --- |
8 |
|
|
3 |
55 |
-X+Y |
37.5 / --- |
9 |
|
|
Install |
|||||
|
SP |
SN |
telescope face |
(tel az / floor az) |
data sheet |
Installed |
|
3 |
57 |
-X+Y |
37.5 / --- |
9 |
|
|
11 |
11 |
-X+Y |
37.5 / --- |
8 |
|
|
26 |
69 |
-X+Y |
37.5 / --- |
12 |
|
Lead person
check that JLG is stowed for telescope motion
Lead person check that dome AC's are ON
Day 2 6/18/03
Lead person
check that dome AC's are OFF
Lead person
check that JLG is stowed for segment exchange
SCHEDULE:
A.M. Remove SP 28, 27, 12 . Cell crew lunch break, Install. 12
P.M. Floor crew lunch break, Install SP 27,.28
Warping : G. Thorkildsen (Austria) will warp segments on 6/19/03.
|
Remove |
|||||
|
SP |
SN |
telescope face |
(tel az / floor az) |
data sheet |
Removed |
|
28 |
89 |
-X-Y |
157.5 / 165 |
3 |
|
|
27 |
76 |
-X-Y |
157.5 / 165 |
10 |
|
|
12 |
74 |
-X-Y |
157.5 / 165 |
11 |
|
|
Install |
|||||
|
SP |
SN |
data sheet |
Installed |
||
|
12 |
18 |
-X-Y |
157.5 / 165 |
11 |
|
|
27 |
37 |
-X-Y |
157.5 / 165 |
10 |
|
|
28 |
40 |
-X-Y |
157.5 / 165 |
3 |
|
Lead person
check that JLG is stowed for telescope motion
Lead person
check that dome AC's are ON