Segment Exchange Plan For: 6/17/03 & 6/18/03

To:                  Distribution

From:             M. Dahler        

Date:              6/10/03

A primary mirror segment exchange for Keck K1 is scheduled to take place on  6/17/03 and 6/18/03.  The following is a schedule of the exchange and related activities (a detailed engineering observing schedule will be distributed separately).

EXCHANGE:

 

Day 1

Day 2

Segment Position:

26

11

3

28

27

12

Remove Serial No.:

27

17

55

89

76

74

Install Serial No.:

69

11

57

40

37

18

SUPPORT ACTIVITIES:

Aluminization is complete: (Tim Saloga)

Sensor maintenance is completed: S. Doyle

Segment crane check-out, [ CARA Doc. 159] Completed: (A. Agliam)

CREW:

Team Leader:

N. Felton (Floor)

Mirror Technicians:

C. Hunt (Cell)

P. Crivello (Cell)

T. Arruda(Cell)

R. DeMotta (Cell)

T. Saloga (Floor)

M. Nakata (Floor)

Sensor Technicians:

D. Chan, J. Killian (Swing-out) Day1

D. Chan, G. Thorkildsen(Swing-out) Day2

S. Doyle, E. Appleby(Swing-in) Day1

S. Austria, D. Chan(Swing-in) Day2

S. Doyle (Appleby) (Warping) 6/18/03

G. Thorkildsen (Austria) (Warping) 6/19/03

Crane Operator:

A. Agliam, D. Scofield (Day 1)

A. Agliam, M. Devenot (Day 2)

Early Starts and Late Finishes:

 Mirror, Crane and Sensor Swing-out crew start 2 hours EARLY.

 Sensor technicians may stay LATE for sensor swing in.



Distribution:


D. Chan

R. Cohen

A. Contos

K. Kinoshita

H. Lewis

R. Matsuda

D. McBride

B. Moskitis

T. Nordin

B. Schaefer

J. Vause

P. Wizinowich


Crew:


A. Agliam

C. Hunt

D. Chan

D. Scofield

E. Appleby

G. Thorkildsen

J. Killian

M. Devenot

M. Nakata

N. Felton

P. Crivello

R. DeMotta

S. Austria

S. Doyle

T. Arruda

T. Saloga


ACTIVITY SCHEDULE FOR exchange dates: 6/17/03 and.6/18/03

  MIRROR SEGMENT EXCHANGE

Day 1  6/17/03

Lead person check that dome AC's are OFF                                       

Lead person check that JLG is stowed for segment exchange           

SCHEDULE:

A.M. Remove SP. 26,  11,  3   Cell crew lunch break, Install 3.

P.M. Floor crew lunch break, Install SP 11, 26.

Warping : S. Doyle (Appleby) will warp segments on 6/18/03.

Remove

         

SP

SN

telescope face

(tel az / floor az)

data sheet

Removed

26

27

-X+Y

37.5 / ---

12

11

17

-X+Y

37.5 / ---

8

3

55

-X+Y

37.5 / ---

9

Install

         

SP

SN

telescope face

(tel az / floor az)

data sheet

Installed

3

57

-X+Y

37.5 / ---

9

11

11

-X+Y

37.5 / ---

8

26

69

-X+Y

37.5 / ---

12

Lead person check that JLG is stowed for telescope motion  

Lead person check that dome AC's are ON    

Day 2  6/18/03

Lead person check that dome AC's are OFF                                       

Lead person check that JLG is stowed for segment exchange           

SCHEDULE:

A.M. Remove SP 28, 27,  12  .   Cell crew lunch break, Install. 12

P.M. Floor crew lunch break, Install SP 27,.28

Warping : G. Thorkildsen (Austria) will warp segments on 6/19/03.

Remove

         

SP

SN

telescope face

(tel az / floor az)

data sheet

Removed

28

89

-X-Y

157.5 / 165

3

27

76

-X-Y

157.5 / 165

10

12

74

-X-Y

157.5 / 165

11

Install

         

SP

SN

   

data sheet

Installed

12

18

-X-Y

157.5 / 165

11

27

37

-X-Y

157.5 / 165

10

28

40

-X-Y

157.5 / 165

3

Lead person check that JLG is stowed for telescope motion  

Lead person check that dome AC's are ON