Segment Exchange Plan For: 7/8/03 & 7/9/03
From: Mike Dahler
Date: 6/30/03
A primary mirror segment exchange for Keck K1 is scheduled to take place on 7/8/03 and 7/9/03. The following is a schedule of the exchange and related activities (a detailed engineering observing schedule will be distributed separately).
![]()
EXCHANGE:
|
Day 1 |
Day 2 |
|||||
|
Segment Position: |
29 |
13 |
4 |
31 |
30 |
14 |
|
Remove Serial No.: |
21 |
52 |
60 |
83 |
36 |
32 |
|
Install Serial No.: |
27 |
24 |
55 |
89 |
76 |
74 |
![]()
SUPPORT ACTIVITIES:
Aluminization will be complete prior to the exchange: (Tim Saloga)
Sensor maintenance will be complete prior to the exchange: () Name: S. Doyle, G. Thorkildsen
Segment crane check-out, [CARA Doc. 159] Completed: (Allen Agliam)
CREW:
Team Leader:
M. Dahler (Floor)
Mirror Technicians:
C. Hunt (Cell)
P. Crivello (Cell)
M. Nakata (Cell)
N. Felton (Floor)
T. Saloga (Floor)
R. Demota (Floor)
T. Arruda (Floor)
Sensor Technicians:
G. Thorkildsen, T. Nordin (Swing-out) Day 1
G. Thorkildsen, J. Killian (Swing-out) Day 2
S. Doyle, S. Austria (Swing-in) Day 1
S. Doyle, S. Austria (Swing-in) Day 2
T. Saloga, G. Thorkildsen (Warping) 7/9/03
S. Doyle, S. Austria (Warping) 7/10/03
Crane Operator:
D. Scofield, A. Agliam (Day 1)
D. Scofield, M. Devenot (Day 2)
![]()
Early Starts and Late Finishes:
: Mirror, Crane and Sensor Swing-out crew start 2 hours EARLY.
: Sensor technicians may stay LATE for sensor swing in.
![]()
Distribution:
D. Chan
R. Cohen
A. Contos
K. Kinoshita
H. Lewis
R. Matsuda
D. McBride
B. Moskitis
T. Nordin
B. Schaefer
J. Vause
P. Wizinowich
Crew:
M. Dahler
C. Hunt
P. Crivello
M. Nakata
N. Felton
T. Saloga
R. DeMotta
T. Arruda
S. Doyle
G. Thorkildsen
J. Killian
S. Austria
A. Agliam
D. Scofield
M. Devenot
ACTIVITY SCHEDULE FOR exchange dates: 7/8/03 and.7/9/03
MIRROR SEGMENT EXCHANGE
Day 1 7/8/03
Lead person
check that dome AC's are OFF
Lead person
check that JLG is stowed for segment exchange
SCHEDULE:
A.M. Remove SP. 29, 13, 4 Cell crew lunch break, Install 4.
P.M. Floor crew lunch break, Install SP 13, 29.
Warping : T. Saloga, G. Thorkildsen will warp segments on 7/9/03.
|
Remove |
|||||
|
SP |
SN |
telescope face |
(tel az / floor az) |
data sheet |
Removed |
|
29 |
21 |
-X-Y |
157.5/165 |
4 |
|
|
13 |
52 |
-X-Y |
157.5/165 |
2 |
|
|
4 |
60 |
-X-Y |
157.5/165 |
1 |
|
|
Install |
|||||
|
SP |
SN |
telescope face |
(tel az / floor az) |
data sheet |
Installed |
|
4 |
55 |
-X-Y |
157.5/165 |
1 |
|
|
13 |
24 |
-X-Y |
157.5/165 |
2 |
|
|
29 |
27 |
-X-Y |
157.5/165 |
4 |
|
Lead person
check that JLG is stowed for telescope motion
Lead person check that dome AC's are ON
Day 2 7/9/03
Lead person
check that dome AC's are OFF
Lead person
check that JLG is stowed for segment exchange
SCHEDULE:
A.M. Remove SP 31, 30, 14 . Cell crew lunch break, Install. 14
P.M. Floor crew lunch break, Install SP 30,.31
Warping : S. Doyle, S. Austria will warp segments on 7/10/03.
|
Remove |
|||||
|
SP |
SN |
telescope face |
(tel az / floor az) |
data sheet |
Removed |
|
31 |
83 |
-X-Y |
157.5/165 |
7 |
|
|
30 |
36 |
-X-Y |
157.5/165 |
5 |
|
|
14 |
32 |
-X-Y |
157.5/165 |
6 |
|
|
Install |
|||||
|
SP |
SN |
data sheet |
Installed |
||
|
14 |
74 |
-X-Y |
157.5/165 |
6 |
|
|
30 |
76 |
-X-Y |
157.5/165 |
5 |
|
|
31 |
89 |
-X-Y |
157.5/165 |
7 |
|
Lead person
check that JLG is stowed for telescope motion
Lead person
check that dome AC's are ON