16 June 2003, Monday

Keck I Engineering plan

Split night:

"Wayne Dahl is planning to come in to his office whenever Terry S. (OA) finishes the first pointing test (~2 AM), generate a new pointing model using those data, and have Terry take as much of another pointing test as he can for the rest of the night. So far as we know, this will be the first time a new pointing model has been tested *immediately* after it was generated" - F. Chaffee

Below is an email from Kyle K. with TPTT plans for addressing the K1 pointing problems

The TPTT formulated the following plan today to address the recurring K1 telescope pointing problems:
Wayne Dahl (WD) was tasked to mathematically model Ron Quick's pointing model correction recommendations and upload the new correction algorithm for tonight's observing. WD concluded that adding this correction algorithm (derived over only 1/4 of the sky) will not improve telescope pointing over the entire sky (it actually makes it worse). See correspondence from WD dated 6/16/03 (utilizes the new correction algorithm on data collected on a complete 3/15/03 pointing test). The following engineering plan was formulated based on these conclusions: