ESI Commissioning Schedule
Following is a daily schedule for ESI commissioning, as envisioned at the
beginning of the commissioning period.
Monday, 26 July 1999
Tasks:
|
Check ability to manually define ESI module.
|
|
Survey ESI module.
|
|
Receive first ESI air shipment at Kona airport.
|
|
Transport shipment #1 to summit.
|
|
Offload shipment #1 into K1 dome.
|
|
Meet ESI personnel and have a short briefing.
|
Notes:
Survey was not useful except for practice. The bar crossing the center of
the ESI module was being held too tightly, and flexed as the rotator
was rotated. Redesign will be implemented tomorrow.
RWG, 7/28/99
Tuesday, 27 July 1999
Tasks:
|
Survey ESI module. (Seerveld, Saloga, Goodrich, Bell)
|
|
Move defining points per survey's prescription. (Bell, Crivello, Goodrich)
|
|
Unpack ESI crates onto dome floor and into Instrument Lab. (Cowley, Radovan,
Lewis, Kanto, Mason, Noe)
|
|
Begin main frame assembly. (Cowley, Radovan, Lewis, Kanto, Noe)
|
|
Install collimator actuators. (Cowley, Radovan, Lewis, Kanto)
|
Notes:
Survey with redesigned bar across module shows little evidence for
torsion and hysteresis. Results are a small (~5mm) decenter, and relatively
large (10 arcminute) tilt errors. Decision was made to ignore decenter
for now, and to keep one of the four defining points out of contact (so
that we are only defining using three of the points. The first shimming
involves grinding larger slots in the module to allow room for the
required motion. We also decided to let the bottom left defining point
(DP4 in our nomenclature) float free, and to always adjust so that the bottom
right DP (DP3) is zero. Hence we never have to move the lower defining
points, which would involve lifting the module on the crane.
RWG, 7/28/99
Wednesday, 28 July 1999
Tasks:
|
Survey ESI module. (Seerveld, Saloga, Bell)
|
|
Adjust module defining points. (Bell, Crivello)
|
|
Set up ESI computers. (Jon Chock)
|
|
Assemble crane in Instrument Lab. (Radovan)
|
|
Arrival of Andy Sheinis and Jim Burrous.
|
|
Arrival of second air shipment.
|
|
Truck shipment #2 to summit. (Sheinis, Burrous, Noe)
|
|
Offload shipment #2.
|
|
Fabricate new parts for cable wrap to minimize interference with mirror
support structure. (Lewis, Kanto)
|
|
Install optics in OSS (except camera). (Cowley, Radovan)
|
Notes:
Air shipment #2 was bumped from its United flight, and did not leave San
Francisco. Survey of module delayed due to work on MIRLIN problem with
chopper and NIRSPEC move from LNas to RNas, but analysis indicates
the module was shimmed the wrong direction yesterday. Jon Chock has
ESI computers up and running.
RWG, 7/29/99
Thursday, 29 July 1999
Tasks:
|
Adjust defining points. (Bell, Crivello)
|
|
Continue survey of module. (Seerveld, Saloga, Bell)
|
|
Pick up shipment #2 at Kona airport. (Sheinis, Noe)
|
|
Offload shipment #2.
|
|
Unpack shipment #2. (Cowley, Sheinis)
|
|
Align collimator actuators. (Burrous)
|
|
Power motors and check OSS stages. (Burrous)
|
|
Finish cable wrap modifications. (Lewis, Kanto)
|
Notes:
Surveys giving conflicting and ambiguous results. Need to do some sanity
checks tomorrow.
RWG, 7/29/99
Friday, 30 July 1999
Tasks:
|
Address problems with survey repeatability. (Seerveld, Bell, Goodrich)
|
|
Adjust defining points. (Bell, Felton)
|
|
Continue survey of module (last one?). (Seerveld, Saloga, Goodrich, Bell)
|
|
Check ESI accounts, automounter, etc. on ESI computers. (EChock)
|
|
Start camera assembly. (Sheinis)
|
|
Power up all OSS stages. (Burrous)
|
|
Install collimator into OSS. (Sheinis)
|
Notes:
Still some problems with surveys, but have converged on the correct
signs for adjustments, and have determined a precise methodology
for the analysis of measurements. Surveys will continue tomorrow.
All camera lens elements inspected
and found to be in good shape. ESI crew will work Sunday to get
mainframe installed in module.
Work on filter wheel done today, accelerating the schedule for that
component.
RWG, 7/30/99
Saturday, 31 July 1999
Tasks:
|
Continue survey. (Seerveld, Saloga, Bell)
|
Notes:
Survey completed with final measurements: 100 arcsec off in tilt (within
the 120 arcsec ESI request) and 0.5 mm decenter (within the 2 mm ESI
request). May do one more tilt adjustment Monday.
Sunday, 1 August 1999
Tasks:
|
Install mainframe in rotator (accelerated from Monday).
|
|
Install cable wrap.
|
|
Test fit cable wrap.
|
|
Start camera assembly. (Sheinis)
|
|
Test TV camera drives. (Burrous)
(Bell, Cowley, Radovan)
|
Notes:
With just the backend of ESI in the rotator, the module is very unbalanced
and would not define readily. Will need to counterweight before reinstalling
Monday for collimator alignment.
Monday, 2 August 1999
Tasks:
|
Shutdown ESI computers and install new electronics rack. (Chin)
|
|
Install counterweights on ESI.
|
|
Install mainframe in rotator. (Cowley, Radovan)
|
|
Start asssembly of OSS.
|
|
Install electronics boxes.
|
|
Assemble camera to OSS.
|
|
Install OSS into mainframe.
|
|
Perform fit check including cable wrap.
|
|
Continue camera assembly.
|
Notes:
Several tasks delayed until after ESI alignment finished.
Still a bubble in cell 3, which we will try to get out before assembling
the camera further.
Tuesday, 3 August 1999
Tasks:
|
Continue ESI alignment.
|
|
Install filter wheel.
|
|
Start preparations for wiring.
|
|
Start installation of TV system. (Radovan)
|
|
Install cable takeup.
|
|
Remove module from telescope.
|
Notes:
Succeeded in accurately aligning the collimator to the ESI rotator.
Did not have time to set up the theodolite on the telescope optical axis,
but did a quick check with just the ESI alignment scope. Did not have
time to digest the results, but the f/40 crosshairs looked like they
were right where they should have been. (The tertiary tower crosshairs
are offset from the telescope axis, so some thought needs to be given
to the sign of the observed offset.)
Wednesday, 4 August 1999
Tasks:
|
Finish installation of TV system. (Radovan)
|
|
Move instrument and module to dome floor.
|
|
Continue wiring preparations.
|
|
Start installation of calibration system.
|
Notes:
Removed ESI module from Nasmyth deck to dome floor, placing it on a
temporary handler. Finished camera assembly, installed OSS into
main frame, and installed camera into OSS. Crew is all set to
assemble rest of the instrument on dome floor.
Thursday, 5 August 1999
Tasks:
|
Continue installation of calibration system.
|
|
Continue wiring.
|
Notes:
Excellent progress today. Two of three electronics boxes mounted.
Received word from Santa Cruz that the ESI
dewar and CCD will be arriving Sunday, 8 August, as planned.
Friday, 6 August 1999
Tasks:
|
Finish installation of calibration system.
|
Notes:
Sunday, 8 August 1999
Tasks:
|
Air shipment #3 arrives with Kibrick and Clarke. Includes final computer
(database computer) and possibly dewar with CCD.
|
|
Transport shipment #3 to summit.
|
Notes:
Monday, 9 August 1999
Tasks:
|
Wire collimator actuators and test. (Burrous)
|
|
Begin optical alignment.
|
|
Unpack shipment #3. (Cowley, JChock)
|
|
Pump dewar.
|
|
Begin dewar cooldown.
|
|
Install database computer. (JChock)
|
|
Initial internal optical alignment.
|
|
Install camera shutter.
|
|
Pot front window of ESI.
|
|
Finish module plumbing (sometime this week). (Crivello)
|
|
Install defining point motors (sometime this week). (Bell, Crivello)
|
|
Pin defining points (sometime this week). (Bell, Crivello)
|
Notes:
Excellent progress on wiring; only the TV and calibration sources remain to do.
Cable wrap modifications still ongoing; should be completed tomorrow.
The dewar is on the pump, and cooling should start tomorrow rather than
today. Rather than a full-up internal optical alignment, we are instead
measuring how far out various components are. Once we get the dewar
installed (Wednesday) we will see how the image quality looks, and if
it needs any fine tuning. Some CARA tasks above will be done as time and
access to the module permit, probably later in the week.
Tuesday, 10 August 1999
Tasks:
|
Final optical alignment checks. (Sheinis)
|
|
Route plumbing and electrical connections on instrument.
|
|
Pull fibers from Nasmyth deck to computer room.
|
Notes:
Again excellent progress today, including cooldown of dewar and first images
taken with CCD. The dewar was mounted on the instrument, and most of
the electronics are connected. Computer integration continues at HQ.
Wednesday, 11 August 1999
Tasks:
|
Connect glycol and test.
|
|
Install nose cone.
|
|
Install dewar on instrument and confirm communications.
|
|
Install front window and hatch.
|
Notes:
Alignment work continued today, with more planned for tomorrow. A special
fixture to check alignment of the pupil on the grating will be
constructed. The calibration system (the "Torpedo") was installed, but
some alignment and wiring remains to be done.
Thursday, 12 August 1999
Tasks:
|
Install remainder of cladding.
|
|
Start spectrograph testing on dome floor. (Sheinis, Clarke, Goodrich)
|
|
Set up guide camera access from waimanu.
|
Notes:
The TV camera was removed for alignment and reinstalled. Power supplies
for calibration lamps were wired, and the glycol system was tested.
Preparations and measurements for further optical alignment continue.
Friday, 13 August 1999
Tasks:
|
Continue spectrograph testing. (Sheinis, Clarke, Goodrich)
|
|
Radovan, Lewis, and Kanto return to Santa Cruz.
|
|
Move module to Nasmyth deck.
|
Notes:
The major item was moving the instrument to the Nasmyth deck, which
went without a hitch. There is a junction box on the module which
needs to get relocated as it interferes with the electronics boxes
for ESI. Its disposition will be determined after the e-box covers
are installed and the clearance measured. The guide camera was
successfully run from waimanu, although we need some jumper fibers to
get from various computers to others. The coax was routed back up
to the Nasmyth deck, and the first echellette spectra were taken.
The echelle pattern fell pretty much in the correct place on the
detector, which is encouraging.
Monday, 16 August 1999
Tasks:
|
Start system integration testing. (Clarke, Sheinis, EChock, Goodrich)
|
|
Start servo tuning. (JChin)
|
Notes:
Instrument balance was done today, as a preliminary to servo tuning.
Tuesday, 17 August 1999
Tasks:
|
Continue systems integration testing. (Clarke, EChock)
|
|
Continue servo tuning.
|
Notes:
Wednesday, 18 August 1999
Tasks:
|
Install ESI in telescope, check balance, clearances.
-
Keck crew (Bell, Goodrich, ET) leaves HQ early (6 a.m.).
ESI crew to go to summit with the early Keck crew.
-
Move telescope to horizon, install horizon lock.
-
Move to RT4 position (LRIS).
-
Remove LRIS to deck and cable up.
-
Move to RT3; install ESI in telescope.
-
Remove weight (nominally 200 lbs.) from tertiary tower.
(Add weight to LRIS module before next LRIS installation.)
-
Install ESI in telescope and define.
-
Add snubber to cable wrap arm.
-
Check Z balance.
-
Check clearance with handrails, platform.
-
Check clearance through yoke.
-
Balance in Y.
-
Time permitting, check behavior of cable wrap as telescope is slewed. Does it
oscillate, shake
the camera, etc?
-
Remove ESI from telescope.
-
Move to RT1, install transfer module in telescope.
-
Move to RT2, install tertiary mirror.
-
Check Z balance.
-
Check Y balance.
-
Continue with checkout for the night's observing.
|
Notes:
Because of an unexpectedly large instrument weight, today's work has
been postponed until next Wednesday. Instead, we weighed the LRIS
module and the ESI module, and measured the offset of the ESI module's
center of gravity from the bearing plane (-2.5 inches).
Baffles were all installed and most of the cladding (minus some small
pieces), are installed.
The dewar was moved in piston to get it to the nominal focal plane.
The collimator was also moved in piston to get the nominal focus
to the middle of the adjustable range.
Thursday, 19 August 1999
Tasks:
|
Survey for position of telescope pupil on grating.
-
Keck crew (Bell, Goodrich, ET) leaves HQ early (5 a.m.).
ESI crew to summit later if desired.
-
Telescope at horizon, horizon lock in.
-
Move to RT2, remove tertiary mirror from telescope.
-
Move to RT1, remove transfer module.
-
Install bar on tertiary tower rails at vertex of mirror.
-
Remove f/15 secondary.
-
Install f/40 secondary.
(Probably do not need to cable it up and initialize it.)
-
Install f/40 crosshairs if required.
-
Move to RT3, setup theodolite on optical axis.
-
Set up and align target on bar, so that it is centered on the entrance
pupil to the telescope.
-
Remove theodolite and install ESI.
-
Measure deviation of pupil on grating.
-
Adjust collimator support to center pupil.
-
Check pupil alignment.
-
Readjust if necessary, until we run out of time or we get it right!
-
Remove ESI module to deck.
-
Remove bar from rails.
-
Move to RT1, install transfer module.
-
Move to RT2, install tertiary.
-
Remove f/40 secondary.
-
Install f/15 secondary.
-
Continue with normal checkout for night's observing.
|
|
Measure and mark cable lengths with ESI at the maintenance position
on the Cassegrain platform.
|
|
Test ESI connections on the telescope.
|
|
Piston dewar to optimal focal position.
|
|
Piston collimator to middle of adjustable range.
|
|
Add remaining baffles.
|
|
Final module wheel adjustment.
|
|
Install seismic pins.
|
|
Check servo tuning in telescope, time permitting.
|
Notes:
Alignment went fairly well, with some glitches. The module defined fairly
well except that two of the defining points were interchanged, and two of
them moved the wrong direction. A more major problem was encountered in
removing the module. The groove did not release until the module was
rocked back and forth. We then had problems getting the module out
of the tertiary tower. The module was resting on various things: the air
bag edges were catching the module, the wheel housing was resting on the
rails, two bolt heads were catching under the +X side of the module,
and a nut on the +X side of the module was catching the steel flooring
and gouging a path through it. More time needs to be spent adjusting
the module wheels and making sure that the module installs and removes
easily and positively.
The ESI instrument alignment went well, and initial indications are
that the misalignment is consistent with Andy's previous determination.
That determination indicated that the bearing to telescope axis misalignment
was in the same direction as the instrument to module misalignment,
meaning they added together.
The ESI guide camera was not made to work from the telescope connections.
Friday, 20 August 1999
Tasks:
|
Continue systems integration testing. (Kibrick)
|
|
Continue servo tuning (until 1 p.m.).
|
|
Work on infrastructure for adding weight to the transfer module.
|
|
ESI work.
|
Notes:
Hector fixed the four broken fibers and with Jim Burrous tested their
throughput. All went well with that. The PXL problems were tracked
down to a faulty software module. The back of the collimator cover was
blackened, the calibration lamps reaimed to the field center, and the
grating baffle installed. The ESI crew will work over the weekend so
that CARA can work on the module Monday and Tuesday.
RWG, 8/23/99
Saturday, 21 August 1999
Tasks:
|
Retilt grating to optimize energy distribution in
echellete mode. (Sheinis, Burrous)
|
|
Repoint camera such that wavelength scale is per optical design. (Sheinis,
Burrous)
|
|
Install more baffling to eliminate an annoying arc reflection. (Cowley)
|
|
Measured spot sizes and wavelength locations. (Sheinis, Kibrick)
|
Notes:
Also lubricated the imaging flat drive screw and cleaned a smudge off
one prism.
RWG, 8/23/99
Sunday, 22 August 1999
Tasks:
|
Final wiring and testing of temperature sensors. (Burrous)
|
|
Final cladding installation. (Sheinis, Burrous)
|
|
Spare part inventory,
tool packing, and cleanup (Cowley, Sheinis, Burrous)
|
Notes:
Monday, 23 August 1999
Tasks:
|
Remove remainder of tertiary tower weight (~800 lbs. total).
|
|
Install same weights on tertiary module.
|
|
Balance telescope.
|
|
Continue work on adjusting ESI module's wheels and defining.
|
Notes:
Tuesday, 24 August 1999
Tasks:
|
Continue work on adjusting ESI module's wheels and defining.
|
|
Add more weight to transfer module (~700 lbs.)
|
|
Add weight to secondary socket (~400 lbs.).
|
|
Balance telescope.
|
|
Continue systems integration tests.
|
|
Continue servo tuning on deck if required.
|
Notes:
Wednesday, 25 August 1999
Tasks:
|
Install ESI in telescope, check balance, clearances.
-
Move telescope to horizon, install horizon lock.
-
Move to RT4 position (LRIS).
-
Remove LRIS to deck and cable up.
-
Move to RT3; install ESI in telescope.
-
Install ESI in telescope and define.
-
Add snubber to cable wrap arm.
-
Check Z balance.
-
Check clearance with handrails, platform.
-
Check clearance through yoke.
-
Balance in Y.
-
Time permitting, check behavior of cable wrap as telescope is slewed. Does it os
cillate, shake
the camera, etc?
-
Remove ESI from telescope.
-
Move to RT1, install transfer module in telescope.
-
Move to RT2, install tertiary mirror.
-
Check Z balance.
-
Check Y balance.
-
Continue with checkout for the night's observing.
|
|
Trim balance on tertiary module to match ESI's.
|
Notes:
Z balance done today, Y will be attempted tomorrow. The module is not defining
well, and the air bags will not handle the extra load. Late today new air
bags are arriving in Waimea. They will be installed tomorrow morning.
Servo tuning is complete.
Thursday, 26 August 1999
Tasks:
|
Cut coax and AC power cables to length and terminate. (Burrous)
|
|
Install new air bags. (Bell)
|
|
Balance in Y.
|
|
Check clearances past Cassegrain platform and through yoke. (Bell)
|
|
Install safety pin. (Bell, Felton)
|
|
Make new air line.
|
|
Fix more broken fibers.
|
|
Install protective guard over fiber positions on Nas. deck.
|
|
Install protective guard over fiber positions on telescope.
|
|
Check with Seerveld about last adjustment of module during
module-to-telescope alignment.
|
|
Relocate junction box.
|
|
Tie up cables on module.
|
|
Continue servo tuning on deck if required..
|
Notes:
Friday, 27 August 1999
Tasks:
|
Work on tasks not finished yesterday.
|
|
Continue systems integration tests.
|
|
Continue servo tuning.
|
Notes:
Saturday, 28 August 1999
Tasks:
|
Contingency, last minute preparations for commissioning.
|
Notes:
Sunday, 29 August 1999
Tasks:
|
First night of commissioning run.
|
|
Determine pointing origins, image handedness and rotation, scale.
|
|
Take MAlign calibration data.
|
|
Take throughput data for echellette mode.
|
Notes:
Monday, 30 August 1999
Tasks:
|
Night 2 of commissioning.
|
|
Take more throughput data.
|
Notes:
Tuesday, 31 August 1999
Tasks:
|
Night 3 of commissioning.
|
Notes:
Wednesday, 1 September 1999
Tasks:
|
Night 4 of commissioning.
|
Notes:
Thursday, 2 September 1999
Tasks:
|
Remove from telescope to RT2, cable up on deck.
|
Notes:
Last modified: Fri Jan 8 21:28:48 HST 2010