As of 18 June 2007, NIRC will be warmed to ambient temps between
observing runs. NIRC be cooled to operating temps starting 2-3 weeks
before and observing run. Below are procedures to follow when warming
and cooling NIRC.
- Login to maili (instrument host) as nirc
- Turn on level power to the detector:
p3/det/lvlon
- Change to the temperature log directory:
cdlog
- Monitor the temperatures incrementing every 5 min. using the
command:
tail -f TempLog.dat
and keep an eye on the temperatures are in Kelvins. Ambient temps are
around 273 K.
- When NIRC warms to -180 C (187 K), attach a vaccum pump to NIRC
and begin pumping on the dewar.
- Pump for at least two days
- After ambient temperatures are reached, turn off level sensor.
~nirc/p3/det/lvloff
- Continue to pump on the dewar for atleast two days.
- Valve off the dewar and turn off the pump
- Back fill slowly with dry Nitrogen.
Notes:
- If the detector temperature exceeds 275 K cut power to the
instrument (GNIRS law)
- Warm up should take approximately 2 days after LN2 runs out.
Guidlines:
- NIRC will be warmed to ambient temperatures if the time between
runs is more than six weeks.
- If the schedule indicates a warm-up is possible, NIRC will not be
filled with cryo the day following the last night of observing.
- 5 weeks before the run, place NIRC on the pump
- 4 weeks before the run, warm fill with LN2
- A few days before the run, fill inner can with LHe.
|
|