NIRSPEC Reliability Improvement 
Progress report: 7 Jan 2004

Overview:

A month ago, we described the project as being at something of a crossroads.  To some extent this is still true,  since phase I is taking longer to complete than estimated, and we are still in the early stages of phase III.    The past month included the Christmas holidays/slowdown and some team members took vacation time.  Despite this, there has been some noteworthy progress.    We have focussed our efforts on three of the six tasks which make up this project.

Ia.  Speeding recovery from server crashes:

In terms of nearness to completion, this task is roughly in the same state as at the last report.    This statement belies the fact though that much work has been accomplished during the reporting period.    Of the two remaining subtasks, one is still active and the other has been deferred.

IIa.  Upgrade instrument host:

To some extent this task has moved into the background with little progress during the reporting period, and none anticipated until mid-January at the earliest.    We do plan to return this task to the foreground though as soon as resources are available.

IIb.  Correlation research:

This task continues as a pure background task.

IIc.  Crash free periods:

Investigation of day logs have not (yet?) revealed any hardware changes that represent a smoking gun.   Investigation of other logs and software records continues although largely as a background task.

IId.  Characterize communications chain:

Although steady progress has been made on this task, the schedule has had to be revised due to the later than anticipated delivery of the fiber attenuator, and the difficulty in obtaining a SCSI analyser.

IIIa.  Reduce communications traffic:

A month ago, a new version of the server which reduces the frequency of motor commands had just been finished and awaited testing.   At that time, work on the rotator code was envisioned as beginning in early to mid January.

Issues and Concerns: