NIRC-2 Interface Document and Pre-Commission Tasks

updated 12 Sep 2000 rdc


This is the interface document for the Keck II telescope and AO Facility to NIRC-2 interfaces. This document covers the opto-mechanical details associated with both mounting the NIRC-2 system in the AO enclosure on the Nasmyth platform, and interacting with the AO system for normal operation. In addition, this will cover electrical power, communication needs (e.g., ethernet, fiber cables, etc.), cooling, size and space for electronics, and those maintenance items that impact the design of the AO enclosure. This document was converted into table form from the original paragraph form on the Keck AO web page.

 
NIRC2 Interface Items
Location  Drawing /
Spec
Action
red: action needed
green: complete
Rough Estimate of Manpower 
Requirement
Status
1.0 Optics 
Keck AO notes, KAON link
- _ _ - -
1.1 Focal ratio and 
pupil location
AO Bench KAON 107 Measure with IR laser
S. Acton
2 day
2 persons
TBD
1.2 Pupil motion with 
chopping and steering
300mm
from AO bench
_ Determine Pupil Stability
S. Acton
Study pupil stability problem,
Implement solution.
S. Acton
Test AO system without secondary baffle
21 days
3 persons

1 day
4 persons

TBD
1.3 Depth of beam
AO Bench _ _ - _
1.4 Optical axis height
305mm
above AO
_ Measure with IR laser
S. Acton
see para. 1.1 TBD
1.5 Change in focal plane 
position due to ADC
LNAS _ _ - _
1.6 Ghost images and 
emissivity from dichroic
AO Bench - _ _ _
1.7 Alignment system between 
AObench and NIRC-2 
detector plane
N-2 targ/
AO CCD
KAON 46 Need for Active Alignment will be determined during NIRC2 commissioning
S. Acton
R. Campbell
5 days
2 persons
_
1.8 NIRC-2 spectral 
calibration sources
AO Bench _ Determine position and routing of HV  P/S and lines to lamps
R. Campbell
2 days
1 person
_
2.0 Mechanical
_ _ _ _ _
2.1 Physical envelope 
allowed for NIRC2
AO  ACAD Drawing _ _ _
2.2 NIRC-2 mounting 
to Nasmyth platform
LNAS ACAD Drawing
 
Survey pads relative to AO bench
Preliminary elevation measurements of pads
J. Seerveld
D. Medeiros
T. Saloga
2 days,
2 persons
Scheduled for
nov 2000 after
Kcam removal
5 Sep 2000
2.3 Installation and 
alignment ofNIRC-2
LNAS AO enclosure Installation Procedure K. Mathews
R. Campbell
D. Mederios
21 days
5 persons
Upon Delivery
2001
2.4 Weight limit
_ < 1000kg _ _ _
2.5 Overhead hoist
_ CK 1 ton
2Sp 3ph
130" range
CARA review design
Install and test prior to
dewar delivery
D. Medeiros
D. McBride
14 days
3 persons
review
complete
April 2000
2.6 Hoist Support
_ AO enclosure drawing _ _ _
3.0 Electronics
_ Simple Single Line Drawing of NIRC2 Interface _ _ _
3.1 Electronics racks 
for NIRC-2
In AO enclosure
near NIRC-2
Drawing of E-box options

PDF version

Determine characteristics of noise / preamp / cable length
J. Larkin
R. Matsuda
21 days
1-2 persons
In Process
         Secondary Rack
(lakeshore,motor p/s, etc..
Electronics Vault - Design and Build Interface Panel
R. Campbell
R. Matsuda
5 days
3 persons
TBD
3.2 Electrical power-
_ 1.5kW No UPS
D. Mcbride
- _
3.3 Glycol cooling /Heat Exchanger
Glycol to UCLA rack in AO clean room 655-C0005
       -C0006
Install Glycol Module
D. Medeiros
Modify NIRC2 exchanger and Spare.
Evaluate capacity
B. Mason
10 days
1 person
 

3 days
1 person

In Process
3.4 NIRC-2 communication 
requirements (protocols)
_ EtherNet
SCSI
See SW specs
Run Cables in Tel Wrap _ complete
3.5 NIRC-2 interface to 
Observatory (physical)
Interface panel in AO Elec. Vault Fiber & Coax Run Cables in Tel Wrap _ complete
3.6 Grounding and shielding
_ KAON 94 Review design . Troubleshoot  noise problem.
R. Matsuda
J. Larkin
5 days 
2 persons
June 2000
In Process
Hoist control paddle 
and 3 phase power
_ _ CARA to provide 3ph
Power (208 VAC) to
AO roof and connector to
handpaddle
D. Mcbride
5 days
2 persons
TBD
4.0 Cooling and Environmental 
Control
_ _ _ _ _
4.1 Closed cycle refrigeration
mechanical 
room
_ Need connectors for speed controller
D. Mcbride
0.5 days
1 person
TBD
                 CCR He Supply/Return _ _ Install lines in Tel Wrap
D. Mcbride
Install Ts in AO enclosure
D. Mederios
2 days
1 person
TBD
                 CCR Head Power _ _ Need to pull one more
cable thru wrap
D. Mcbride
2 days
2 persons
one cable complete
                 CCR gauges _ _ Evaluate need for gauges
D. Mcbride
K. Mathews
0.5 days
2 persons
_
4.2 Liquid nitrogen 
N/A
N/A _ _ _
4.3 Clean room
_ HEPA Filter System CARA to create clean environment for NIRC2 dewar service, either temporary or permanent for AO bench and NIRC2
S. Acton
P. Wizinowich
D. Mcbride
21 days
3 persons
TBD
4.4 Humidity control
_ _ _ _ _
4.5 Vacuum System
Next to dewar T-connect
KF-40
Need for UPS/generator power for pump
D. Mcbride
Cold Startup Test
K. Mathews
5 days
2 persons

2 days
1 person

TBD
5.0 Software Interfaces
_ Software Design Specification Doc A. Conrad
A. Honey
B. Goodrich
- _
         5.1 User Interface _ scripts/GUI Integrate instrument and AO operation for
astronomer.
R. Campbell
B. Goodrich
21 days
2 persons
In Process
(NIRSPEC)