NIRC2 Service Mission
Purpose: Install filters, trouble shoot temperature readback problems, inspect mechanisms, inspect general state of instrument
Schedule: August, 2003
| 11 Aug, Mon | Install crane boot, check crane operation |
C. Nance |
| 14 Aug, Thu | Remove DSM from K2 -AO | G. Tolleth, B. Mason |
| 20 Aug, Wed | Turn off CCR cold head (compressor stays on), Begin warm-up Monitor warm with temp watch script + normal log | B. Mason, R. Campbell |
| 20 Aug, Wed | Ship NIRC2 container to summit..Unpack | B. Mason |
| 21 Aug, Thu | Prep K2-AO for clean up Remove excess material, seal openings, install dust monitoring instruments, etc. Disconnect electonics Rack, move out of way |
C. Nance, J. Kepa, B. Mason
G. Tolleth, +MT |
| 22 Aug, Fri | Complete thorough cleaning of AO enclosure, seal coude hatch, AO hatch, no other entry from 22Aug until 30 Aug, measure dust particles |
C. Nance, J. Kepa, B. Mason |
| 25 Aug, Mon | Prep work: prepare filters, prepare tools, inspect clean area, release vacuum in dewar, prepare hoist, guides | K. Matthews, R. Campbell, B. Mason |
| 26 Aug, Tue | Open Dewar, install filters | K. Matthews, R. Campbell, B. Mason |
| 27 Aug, Wed | Trouble shoot temperature readbacks, inspect other | K. Matthews, R. Campbell, G. Tolleth |
| 28 Aug, Thu | Contingency day for dewar open | K. Matthews, R. Campbell, B. Mason |
| 29 Aug, Fri | Dewar close, vacuum pump on Reinstall electonics |
K. Matthews, R. Campbell, B. Mason |
| 2 Sep, Mon | CCR's turned on, full speed | B. Mason, R. Campbell |
| 8 Sep, Mon | CCR's speed tuned, Dewar at equilibrium NIRC2 fully operational |
K. Matthews, R. Campbell,B. Mason |
| 16 Sep, Tue | NIRC2 Engineering Night | K. Matthews, R. Campbell |